May 21, 2009

Is agile ERP implementation possible?

Blog posting by Vjekoslav Babi

Agile has been gaining momentum among software development methodologies for past decade or so. Various researches and surveys consistently show that software developed under an agile approach is generally better than the software developed under waterfall approaches.

At the core of any agile approach is an assumption that whatever the requirements might be at the beginning of a project, they won’t be the same at the end of the project. The longer the project, the more truth there is in this assumption. To mitigate this situation, agile methodologies start with smaller sets of requirements, they start small and deliver functionality incrementally in a series of releases. No single release covers all requirements, but every release delivers more than the previous one.

With ERP implementations, we generally don’t subscribe to this idea. And at that, we might be wrong.

We say that ERP implementations are not software development. It’s true, but it might be irrelevant.

We say that with ERP we don’t start from scratch. We must know all the requirements up front because anything we do impacts tens or hundreds of functions. If we just add things incrementally, we might need a lot of rework. So we need a “big picture” up front, we need to design everything in such a way that this huge ERP structure doesn’t collapse.

But no matter what we do, the requirements will change. ERP implementations take 20 months to complete (on average). Do you think your business is going to be exactly the same in 20 months as it is today? Me neither.

ERP implementations start with a fit/gap analysis which detects the gaps between your requirements, and system standard functionality, and then specify how these gaps will be closed. If the specifications are cast in stone, and if you stick to it, after 20 months you’ll might get a system which is not fit anymore.

Recent Panorama’s survey shows that only one out of five companies have realized more than half of expected benefits of the ERP implementation. More than half companies who have implemented ERP have experienced operational disruptions after go live. This is devastating.

From my experience, this has a lot to do with requirements lifecycle.

On the other hand, Standish group’s research over past fifteen years has shown a steady trend towards more predictable and successful software development projects. In 1994, average software project cost overrun was 180%; in 2004 it was 56%. In 1994, average time overrun was 164%; in 2004 it was 84%. In 1994, only 16% of projects came in time on budget; in 2004 it was 29%. Standish group attributes this improvement largely to increased adoption of agile methodologies. Yes, sure, ERP is not software development. But yet…

Where are we with ERP? Still rowing up the waterfall. With today’s turbulent economy, it’s more like rowing up the Niagara Falls. Today, you can’t tell for sure what you are going to do or need in 2 months, let alone 20. Plus, with liquidity issues everywhere, you must make sure that your investment is sound, and that it delivers the expected return; you can’t gamble with 20% chance of achieving 50% of expected benefits.

Adopting an agile approach in implementing ERP might be a solution.


May 14, 2009

On Customer Intimacy...

Article by José Campos (Coauthor of 'Capture and Use the Voice of the Customer for Product Development'):


How many hours have you spent in contact with your customers in the last 90 days? If you are typical of the industry, probably no more than 14 hours or 2 to 3% of your time. Most of us spend little time with our customers. Nor do we spend enough time talking about our customers with others in our organization in order to understand the very people who provide our profits.

Customer Intimacy is the ability to understand and then internalize customer needs in order to generate new value in the form of new products and services. "Value" is always determined by your customers, i.e. nothing is valuable until a customer says so.

Thus, customer intimacy improves profits. Given that it takes purposeful interaction with customers to internalize customer needs, rethinking this time allocation can contribute significantly to creating new value — and by the way, spending only 2% of your time doing it will not work — much more is needed.

Investing the right amount of time with customers is the key to successful new product development. Measuring the outcome of the time spent is also important to track your commitment and progress. It also helps to develop baselines for planning purposes, i.e., how much time you will spend with your customers in the future.

Organizations should measure the outcome or results of interactions with customers, for example, identifying the number of new features, benefits, and key insights discovered from customer interactions. And although operational distractions, such as “fire fighting,” or the lack of clear customer-centric organizational values can keep you from it, the single most important thing you must do is develop customer intimacy to internalize current and future customer needs.


WAYS TO SUPPORT BETTER CUSTOMER INTIMACY

#1 Develop a customer-centric culture.


Having a customer-oriented culture is critical. A culture is more than a set of values listed in a document — it is the observable and rewarded intention and behavior of the company at all levels, from top management on down. It is a vision that is more than another platitude. It is a guiding force that rallies the entire team. A customer-centric culture is one that relentlessly pursues superior value for the customer.

Consider the following ideas:

  • Do the stated and observable values of your organization recognize the importance of the customer?

  • What customer-oriented actions are celebrated? For example, when was the last time someone was recognized for spending lots of time with customers or uncovering a high-leverage customer need?

  • How often is there a team retreat focused solely on talking about your customers, their needs, and their environment?

#2 Establish an effective system for collecting and processing customer knowledge.

Every organization needs a framework for requirements gathering, then interpreting and incorporating customer input and innovating from it (see Table 1). You must be able to understand what your customers are saying—and what they’re not saying—and interpret and internalize the messages. Then the ideas must be incorporated into your company's product development projects.


Investigating is the initial process of requirements gathering. Typical activities include selecting the customers to be contacted, then identifying who will make the contact and what information is needed.


Interpreting involves spending quality time processing the input until clear messages are identified. The amalgamation and integration of the input from many customers will result in clear patterns of customer needs.

Innovating is the ability to go beyond an intellectual understanding of customer needs to an almost visceral belief in them. As someone said, being customer-driven is the ability to see the world as your customers do. In this phase, the intent is to turn your customer input, now that you understand it from the previous phase, into innovation.

Incorporating is accessing the skills, knowledge, and abilities needed to translate customer needs into product design requirements. Here’s where you will convert the innovation into documented new product definitions that drive the product design process.

There are many proven methodologies for product definition available, such as Quality Function Deployment (QFD), KJ, and Hoshin. It is essential to make a long-term commitment to the methodology your organization adopts as most appropriate for itself. In our experience, it is best to start slow and take 2 to 3 years weaving the methodology into your organization. It is, after all, a change in your culture. The new methodology, by definition, will force your team to do things differently through new processes and approaches. Reinforcing the values and desired behavior is critical to achieving true customer centricity — no easy task, but achievable.

The Four I’s Framework for Successful New Product Development


Simply visiting customers is not enough to ensure the incorporation of customer needs into new products. Customer-driven companies have a systemic approach to requirements gathering and processing customer input into useful information that the product design team can apply to product development projects and the creation of new value.


Investigate

Interpret

Innovate

Incorporate

The disciplined approach to requirements gathering and documenting articulated and unarticulated customer needs through a variety of techniques that always include in-depth interviews and some level of observation of the customer’s world.

_____________________

Output

At the end of this phase you should have captured the voice of the customer—the raw data from each of the interviews that you and your team conducted.

Documentation

This should be in the form of notes, photos, video and audiotape, plus the vivid memories that you and your interview teams captured.

The process of organizing the customer data and processing it into a set of prioritized and documented requirements that clearly express customer needs.

_____________________

Output

At the end of this phase, you should have a clear, prioritized and approved list of customer requirements.

Documentation

Generally, this list is relatively short, between two and ten. In some cases it may be longer, but we encourage prioritization to reduce the number of the requirements, which capture the value expressed by your customers.

The process of transforming requirements into one or a few product concepts that will address the articulated and unarticulated customer needs.

_____________________

Output

At the end of this phase you should have innovative solutions that address the requirements expressed by your customers. This phase is where engineering and marketing collaborate to find the solutions and to innovate.

Documentation

The documentation should be a prioritized list of solutions, or a collection of product features that in aggregate (cumulatively) provide a solution.

The disciplined refinement of the product concepts into a single one validated by customer feedback, and its full articulation into a set of features and specifications

________________________

Output

Naturally, the desired output of this phase is a profitable product.

Documentation

On the more practical side, the output of this phase generally is an engineering document, which takes into account the technical trade-offs, the timeline, product design costs and other parameters. Engineering and marketing collaborate to ensure that the customer always wins, that is, that the product has maximum value.

Table 1

#3 Ensure a common purpose by meeting face to face with your customers.


Every one on the product development team, from Marketing to Engineering to Management, must share the same vision of the product. In fact, a team is not a team until there is visible commitment to a common purpose, and the customer is the best point of convergence. Customer focus helps a team rise above functional and corporate barriers. Having all players meet with your customers to share ideas and concerns can solidify the buy-in of each member.


#4 Include all players during the "fuzzy front end."

The period at the beginning of any development project, when there are more questions than answers, often creates considerable confusion. This “fuzzy front end” is a crucial time to bring all team members—including your customers—into the picture because it’s the most convenient and cost-effective time to make and get approval for changes. Once true implementation begins, change becomes painful and may cause severe delays in your schedule.

The Fuzzy Front End, as shown above, occurs at the beginning of every product development project when confusion, mystery, and questions abound. This natural phase is an opportunity to connect with your customers. Also shown are two other important milestones: time-to-market and time-to-profit.

For example, speed of new product development makes it imperative that your product design team has the opportunity to internalize customer needs by interacting directly with them, without our customary filters. These filters, such as design experiences or preference for a particular technology, might make us favor one approach we’re familiar with over another that could better solve the customer’s problem or might encourage us to ignore the wishes of the customer.

Seeing customers in their environment and dealing directly with their problems enhances your engineers’ creativity and helps channel their innovation in the right direction. In fact, your engineers will identify customer needs that marketing can’t—no matter how good your marketing organization might be. Why? Because engineers and other technical personnel view the customer through a different frame of reference. And in a collaborative relationship driven by the mission to provide unprecedented value to the customer, engineering and marketing can create a most helpful “stereo vision” of your customer.

As you involve your product design team, consider the following skills for successful customer interaction:

  • How to select the right customers for interaction

  • How to frame high-value questions, ones without filters and biases

  • How to listen without filters

  • How to translate vague and subjective input into clear design ideas—and constraints

#5 Learn what is missing by talking to your “non-customers.”


We tend to talk to our customer “friends and relatives,” i.e., those customers who are mostly satisfied with our products. In some cases, these customers are the sales team’s favorites and are already well taken care of. While talking to these happy customers is important—it only provides one-dimensional feedback. Talking to other types of customers can provide a fuller picture.


Try talking to some of these customers:

  • Customers you’ve lost

  • Competitors’ customers

  • Future customers

  • Unhappy customers

  • New customers

  • Customers buying much less

  • Customers buying much more

  • Customers who’ve stopped buying altogether

  • Customers who are the most profitable

#6 Measure the right things.


What measures do you currently use to track your level of customer intimacy? Start by tallying the hours you and your team spend in conversation with customers. This simple measure, which can be easily extracted from your calendar/planner, will give you a base line of your organization’s investment in customer intimacy. This will also enable you to set goals to improve your understanding of customer needs. For example, rarely does a 15-minute meeting yield key insights. Plan to spend 2 to 3 hours in dialogue with your customers. This may be hard to do, but the payoff is enormous!


Naturally, measuring the number of hours spent with customers does not guarantee success. You should also track the number of outcomes, the concrete results that can be attributed to customer interaction that enable you to increase the value you provide to them. For example, track the number of high-leverage needs that have been identified, the number of new product features that come out of customer interactions, the speed of decision-making in your organization, and the number of competitive advantages. You decide what to measure, but make sure they are results, not just activities.

#7 Know where you are going.

To transform your organization into a customer-centric team, an overall plan of action is essential. Your commitment to a customer-centered approach should include a master plan, or road map, that outlines the why, how, when, who, and how much. Smaller, more individual action plans can guide easy actions that can be quickly implemented. Create an approach that facilitates small improvements, while you develop and implement your long-term plan.

By making a commitment to incorporate at least one of the ideas above in the next three months, you and your organization can take a significant step towards better customer understanding and improving your ability to meet customer needs. And by focusing on immediate steps and a commitment to customer intimacy for the duration, the time and energy invested can pay off in visible results and a healthier bottom line.

May 7, 2009

World Market for Aircraft MRO to Reach $55.2 Billion by 2015

From preview of a report titled "Aircraft Maintenance, Repair And Overhaul (MRO): A Global Market Report' published by Global Industry Analysts Inc.:

Aircraft Maintenance, Repair And Overhaul (MRO) is a highly volatile market subject to rapid and unexpected changes in economic and international business conditions. Short-term challenges abound in the form of the ongoing economic downturn, high prices, market saturation, slower new aircraft deliveries, shortage of skilled labor, and airline consolidation. The weakness in the global market is presently the result of tight financial conditions, rising fuel costs, falling air traffic demand, and reduced spending on air travel by both households and corporates. Expansion plans, which had started to recede in the early 2008, widened back out as persistent news about deferred aircraft deliveries injected yet another dose of uncertainty into the MRO market. An estimated 1,025 aircrafts were deferred in 2008 and the oldest, most maintenance-demanding aircraft were the first ones in hangar. Nearly 75 percent of the deferred planes were of North America. Gains in Asian MRO market have beleaguered but haven't completely stalled as they have in the United States.

However, as the market recovers poise, strong demand fundamentals will re-emerge to prop up growth. Resurgence of the aviation industry, reduced airfares, greater connectivity, increase in low cost airlines, technological innovations, and expansion in the overall capacity of air seat miles, will drive growth in the medium to long-term. Asian markets will emerge as the hub of activity, for instance, expanding air traffic has already led to the establishment of numerous, low-cost MRO facilities in high growth potential Asian markets including Singapore, China, India and Malaysia. Dramatic proliferation in air traffic and increase in number of passengers has been and will continue to remain an important factor in attracting foreign investment and paving the way for future development. The growth in the domestic as well as international fleet movement has led to a heavy appreciation in the stocks of the aviation industry. This in turn leads to the requirement for an effective maintenance and overhaul system and service structure for aircrafts and their engines.

World market for Heavy Airframe Maintenance is poised to grow at a steady pace over the years 2006 through 2015, as stated by the recent report published by Global Industry Analysts Inc. Engine Overhaul is forecast to grow the fastest in Asia-Pacific over the analysis period.

Key players dominating the market include Air France KLM, Aveos Fleet Performance Inc., AAR Corp, Ameco Beijing, Ametek Inc., Abu Dhabi Aircraft Technologies, Bedek Aviation Group, Delta TechOps, ExelTech Aerospace Inc., Aviation Technical Services Inc., Hong Kong Aircraft Engineering Company, Lufthansa Technik (LHT), MTU AeroEngines, Singapore Technologies Aerospace (ST Aerospace), SR Technics, SIA Engineering Co., Snecma Services, STAECO, TIMCO Aviation Services Inc, and VEM/TAP M&E, among others.


FANGs of Scope Creep

Article by Hans Robbers in gantthead.com

Managing the scope of a project is one of the main instruments to manage the project budget. Over the years I have a developed a more holistic view on scope management, discovering budget overruns are not always due to changes to the functionality but also due to changes in project approach. Another reason is the willingness of the project team to make the project a success and therefore spent time on support activities not foreseen at the start of the project.

As a result I describe scope in terms of FANGs:

  • Functionality
  • Activities
  • Non-functional requirements
  • Governance

This article explains the thinking behind the concept and provides examples and tips to manage each of the aspects.

Functionality

Functionality starts with having the business/functional requirements signed off. It's pretty straightforward as soon as the approval and the sign-off has been obtained. From that moment on, the functionality is under change control. The only potential budget consumer is impact analysis. All projects have a standard change-control procedure in place, which starts with approval for impact analysis. How many of you have a separate budget for impact analysis, irrespectively if the change will be approved?

Besides the additional work that might not be covered in the budget, there is also the fact of distraction that will reduce the productivity--and potentially extend the project time lines. There are two ways to handle impact analysis funding:

  1. Establish a separate contract/budget for impact analysis, outside the project budget. This budget is used to finance impact analysis on a time-and-material basis.
  2. Allocate a percentage of the total project for impact analysis, e.g. 5 percent. In a fixed-price project, this will not be acceptable since there is no control or visibility on the way the money is spent.

Activities

All assignments to project resources, which have no clear deliverables, are considered activities without added value to the functionality:

Timeline-dependent activities

In most cases these activities will increase in effort when the timeline extends. When a change request is raised extending the timelines, the additional effort for these tasks need to be taken into account as well.

  • Project management is a must for a project; however, the scope of project management can be different per project (and therefore the effort required). If a full PMO is required with extensive activities, I would argue this to be a part of project management (it will increase the effort).
  • Configuration Management
  • Quality Assurance

Demand-driven activities

These activities focus on support the customer during certain project phases. There are two options on how to deal with these activities:

  • Maximize the support effort per activity to a number of man days and include that in the project charter or contract.
  • Exclude the activities from the scope and agree on a separate assignment or contract to deal with these activities on a time and material basis. The disadvantage of this option is in case of increased support it might influence your planning if you are using shared resources.

Examples of these kind of activities are:

  • Support to develop test scenario’s, test scripts etc
  • Test support during UAT
  • Training support (to explain the system and to give demonstrations to users)
  • Deployment support (to support the IT organisation to implement the application in new environment)
  • After Go-Live support

Internal project activities

These general activities are focusing on supporting and coaching teams and juniors whereby there are no deliverables defined. This is often resulting in a reduced productivity and therefore an increase in hours. Another example are when the number of (sub) team meetings increases to discuss the approach or solutions.

One of the ways to crosscheck if you have not forgotten any of these activities is to check the RACI matrix and to identify all consulted and informed tasks. The first group is asking your professional experience often without a deliverable; this might range from a quick question to attending workshops or reviewing a solution.

Informed-type tasks are harder to estimate since the team only absorbs information. If a lot of these tasks occur, it means the project is highly interactive with its environment--which will require time from the project team. As a project manager, it is important you allocate time for these activities.

Non-functional requirements

The main focus of the business is to describe the desired solution in terms of functionality. Another important topic is the non-functional requirements--when they are discussed, it is often thought of as the performance requirements. However, from a scoping perspective there is more to take into account. Non-functional requirements can be divided in:

  • Sizing requirements: Performance is a result of this group of requirements. When the project starts there needs to be a clear understanding on the growth strategy of the business in terms of users, usage of the system during the day, volumes of data to be processed, history to be directly available, system resilience, system availability, etc. This will lead to a system configuration, which might require specific technical solution for software development, e.g. parallel processing of certain functions.
  • Application landscape integration: These requirements deal with the interfacing between the applications and the type of interfaces. Will there be a real-time or a batch exchange of information, and what kind of impact does this have on the business requirements?
  • IT integration: Will it be necessary to integrate with specific monitoring systems, single sign on systems, security systems, etc., and what will be the expected effort in these areas to the project? There can also be specific middleware and database querying tools required, impacting the effort or complexity of the total solution.
  • Documentation: Not only user manuals but also technical documentation needs to be delivered. What is the scope and level of detail required?
  • Training: User training is often raised as a topic where there are three models: Train the trainer (a group of super users will be trained, or professional trainers, who will train the rest of the organization); train the end-users (all users will be trained by the project team); training on the job (there needs to be an extensive online manual for help, and during the first weeks there will be consultants available to answer questions during the day). Each of the models has its own impact on estimating and defining activities. Besides the training of the users it might be required to train the IT department because of new hardware, software package or software development language used.

Each of these topics will have its influence on your scope, planning and timeline--and some often appear only at the end of a project when there is already a time squeeze.

Governance

The final part of scope has to deal with governance or the terms of engagement. Not only do the turnaround times for reviews and approvals need to be discussed, but other topics will influence the total effort and timeline of the project:

  • Project Approach: This encompasses all strategic decisions to be made in terms of testing (one user acceptance test or a number), number of releases, introduction of a pilot phase and or shadow runs, roll-out strategy (per department, complete company, all functionality, per location, etc.) and development methodology (waterfall, RUP, agile)
  • Managing External Dependencies: You are dependent on certain deliverables of other parties or departments that are not under the project control, e.g. delivery and installation of hardware, changing legacy systems for interfacing. Availability of these external dependencies determine the project pace and therewith the usage of project resources. Having agreements on external dependencies is crucial for viable planning.

Conclusion

Managing scope is more than just making sure the functional requirements do not change. By applying a holistic view to the scope, it will be possible to deliver a project within time and budget. More importantly, it will make it possible to determine the consequences in an early stage and to have the stakeholders informed in time in such a way that corrective actions could be taken without immediately increasing the project budget and or timeline.